Project Overview:

  • Client: Commercial Premises in Cambridgeshire

  • Location: Cambridge

  • Project Type: Commercial Solar PV System Installation

  • System Size: 34kW

  • System Components:

    • 76 x 440W All Black Solar Panels

    • 1 x 16kW Sunsynk Inverter

    • 1 x 8kW Sunsynk Inverter

    • 1 x 3.68kW Sunsynk Inverter

    • 2 x MyEnergi Zappi Car Chargers

  • Special Requirements:

    • Three single-phase meters required three separate inverters

    • Multiple DNO applications were needed for grid connection approval


Introduction:

A business in Cambridge sought to reduce its operational energy costs and environmental impact by installing a large-scale commercial solar PV system. The goal was to maximise on-site renewable energy generation while also offering staff the ability to charge their electric vehicles (EVs) with free solar power.

Optimum Electrics provided a bespoke solar system design, full project management including multiple DNO (Distribution Network Operator) applications, and expert installation to ensure compliance with all grid connection regulations.


Challenges & Considerations:

  1. Multiple Grid Connections:

    • With three single-phase meters, a standard single-inverter setup was not feasible. Instead, the system had to be divided across three separate inverters (16kW, 8kW, and 3.68kW) to align with the site’s electrical infrastructure.

  2. DNO Applications & Approvals:

    • Each inverter required a separate DNO application. Optimum Electrics managed the entire process, ensuring compliance with grid requirements.

  3. Optimised Solar Design for Maximum Efficiency:

    • The bespoke solar system design had to balance energy distribution across all three meters while maximising on-site consumption.

  4. EV Charging Integration:

    • Two Zappi car chargers were installed to allow staff to charge their electric vehicles directly from solar energy, reducing their commuting costs and promoting sustainable transport.


Installation Process:

1. Solar System Design & DNO Application Management

  • Optimum Electrics designed a 34kW system with 76 all black 440W solar panels, ensuring maximum efficiency and aesthetic integration.

  • Three separate inverters were strategically chosen to distribute the generated power across the site’s existing electrical infrastructure.

  • DNO applications for each inverter were meticulously prepared and submitted, ensuring all regulatory approvals were secured before installation commenced.

2. Installation

  • Panel Installation: The 76 panels were installed across available roof space, optimised for sun exposure.

  • Inverter Installation: The three Sunsynk inverters (16kW, 8kW, and 3.68kW) were installed in designated areas.

  • Electrical Configuration: The system was wired to distribute generated power correctly across the three meters.

3. EV Charger Installation

  • Two MyEnergi Zappi chargers were installed in the staff parking area, configured to prioritise solar energy for vehicle charging.

4. System Testing & Commissioning

  • The entire system underwent rigorous testing to ensure seamless operation, optimal energy distribution, and compliance with grid regulations.

  • Staff were given a demonstration on how to use the Zappi chargers and monitor solar production.


Results & Benefits:

Significant Cost Savings:

  • The business now generates a large proportion of its electricity needs from solar energy, reducing energy bills and insulating against future energy price rises.

Sustainable Employee Benefits:

  • Staff can charge their EVs for free using renewable energy, reducing their commuting costs and carbon footprint.

Environmental Impact:

  • The 34kW system significantly reduces CO₂ emissions, contributing to the company’s sustainability targets.

Future-Proofed Energy Solution:

  • The system is scalable, meaning additional solar capacity or battery storage can be integrated in the future as energy demands grow.


Conclusion:

The 34kW commercial solar installation at this Cambridgeshire business highlights how a tailored solar solution can maximise renewable energy benefits despite complex grid constraints. Optimum Electrics delivered a bespoke system design, managed multiple DNO applications, and provided a seamless installation, ensuring cost savings, sustainability, and employee benefits.

By integrating solar power with EV charging, this project serves as a model for other businesses looking to transition to a greener and more energy-independent future.


Commercial solar installation cambridge

Looking to install a solar PV system on your home or business premises? Contact our team today for expert advise and a free, no obligation quote and solar design.


01733 601698

Comments


bottom of page